New Features Coming Soon for MyScanner Users At Loadscan, we’re always striving to [...]
Inaccurate bulking and compaction factors can add significant costs to all civil projects!
Commonly-used bulking and compaction factor charts provide generic estimates, and don’t necessarily reflect the actual state of the material being excavated. Incorrectly estimated or misunderstood factors can add significant costs to a project due to material measurement inaccuracies. One cubic from the borrow does not translate into one cubic dumped, nor one cubic compacted.
Excavation increases the volume of material, so material from the borrow expands when dumped into the truck bin, into site, or stockpiled. Conversely, material typically shrinks under compaction. Without accurate factors to determine the exact volume of material required to be loaded onto trucks to satisfy compacted contract volumes, supplied volumes may be incorrect and truck capacity not fully utilised.
Typical bulking & compaction factor chart
Material | Typical Bulking Factors | Typical Compaction Factors |
---|---|---|
Clay | 1.3 | 0.8 |
Soil | 1.25 | 0.9 |
Sand & Gravel | 1.12 | 0.88 |
Rock (blasted) | 1.5 | 1.3 |
Material | Typical Bulking Factors | Typical Compaction Factors |
---|---|---|
Clay | 1.3 | 0.8 |
Soil | 1.25 | 0.9 |
Sand & Gravel | 1.12 | 0.88 |
Rock (blasted) | 1.5 | 1.3 |
Bulking and compaction factor charts are only generic estimates and potentially have a high error rate.